Project Duration
Stipulated Date of Commencement
January 28 2021
Stipulated Date of Completion /
Likely Date of Completion August 06 2021
Likely Date of Completion August 06 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 17,690,949.25
Awarded for
₹ 16,900,085.00
Contractors
M/s.MDD Medical Systems (INDIA) PVT. LTD.
Consultants
M/s.frischmann Prabhu (I) PVT. LTD.