Project Duration
Stipulated Date of Commencement January 05 2022
Stipulated Date of Completion /
Likely Date of Completion
January 14 2023
Status
100%
Completed
Cost (₹)
Estimated at ₹ 25,108,748.16
Awarded for ₹ 28,284,599.49

Project highlights

Construction of sewage Treatment Plant

 
Gallery Image
Contractors
M/s.Indage Development Construction Pvt. Ltd.
Gallery Image
Consultants
M/s. FP Project Management.
 
Similar Projects

See Similar Projects

Similar Project

Upgradation of Ward Nos. 120, 123, 124, staff rest rooms and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa : SH – Procurement of additional works/items and medical equipments required for Ward No.125 and Cardiovascular Surgical Operation Theatre – Supply, Installation and Testing and Commissioning of Dialysis Machine

View Project
Similar Project

Additional Works for setting up of Dialysis Unit at New Premises of CHC-Cacora, Curchorem-Goa.

View Project
Similar Project

Cath Lab at Goa Medical College

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.