Project Duration
Stipulated Date of Commencement
September 19 2020
Stipulated Date of Completion /
Likely Date of Completion September 18 2020
Likely Date of Completion September 18 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 132,746,096.00
Awarded for
₹ 131,078,400.10
Project highlights
The project consist of: Recreation of Rooms, Vocational activity rooms, Computer lab, Library, Group Therapy. It also consists of Yoga Rooms, a Recreational Room and muiltiple activity rooms
Contractors
M/s.Tirupati Sarjan Limited
Consultants
M/s. Pankaj Joshi Consultant
(to be foreclosed)
M/s.FPPM is being appointed.