Status
Completed
Contractors
Consultants
Sub Works
This project involved 2 sub works. The details of the same available below
1
Renovations of old IPHB Building to accommodate Goa Commission for Backward Classes
100% completed
Project Duration
Stipulated Date of Commencement
September 08 2004
Stipulated Date of Completion /
Likely Date of Completion October 07 2004
Likely Date of Completion October 07 2004
Status
100%
Completed
Cost (₹)
Estimated at
₹ 350,184.40
Awarded for
₹ 366,922.00
Contractors
M/s. Sandesh C. Naik
Consultants
M/s. Vijaykumar Sawant Associates
2
Renovations of old IPHB Building to accommodate Nursing Hostel and College and Directorate of Food & Drugs
100% completed
Project Duration
Stipulated Date of Commencement
February 27 2004
Stipulated Date of Completion /
Likely Date of Completion December 25 2004
Likely Date of Completion December 25 2004
Status
100%
Completed
Cost (₹)
Estimated at
₹ 39.85 lakh
Awarded for
₹ 39.81 lakh
Contractors
M/s. Sandesh C. Naik and M/s. C. V. Naik & Son
Consultants
M/s. Vijaykumar Sawant Associates
See Similar Projects
Construction of Day Care Centre at Instuitute Psychiatry and Human Behaviour Complex (IPHB), Bambolim Goa
View Project
Major Maintenance work of Goa Medical College & Hospital and Goa Dental College at Bambolim, Goa SH : Maintenance Contract for Cold Storages installed in Blood Bank, Microbiology Department and Central Pharmacy in GMC Hospital Complex Bambolim for three years
View Project
Medical gas & vacuum plant.
View Project