Project Duration
Stipulated Date of Commencement
April 15 2022
Stipulated Date of Completion /
Likely Date of Completion December 14 2022
Likely Date of Completion December 14 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 32,678,364.00
Awarded for
₹ 36,058,328.56
Project highlights
Development of parking space
Contractors
M/s. Indage Development Construction Pvt. Ltd.
Consultants
M/s. KICONS Limited
See Similar Projects
Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in South Goa – SH: Dismantling and buy back of existing Sewage Treatment Plant (STP) and Design, Supply, Installation, Testing and Commissioning of new 30 KLD STP at Community Health Centre, Canacona – Goa
View Project
Renovation/Maintenance of Hospitals, CHC’s, PHC’s, RMD’s under Directorate of Health Services in North Goa SH: Maintenance/ Renovation Work of Sub District Hospital at Ponda, Goa – SITC of Split AC Units
View Project
Supply, Installation, Testing and Commissioning of E. T. O Machine
View Project