Project Duration
Stipulated Date of Commencement January 03 2019
Stipulated Date of Completion /
Likely Date of Completion
August 31 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 47,193,574.50
Awarded for ₹ 62,030,298.77

Project highlights

The project consist of supply and erection of new medical gas line distribution system such as Oxygen Manifold system, Air compressors, Vaccumm Plant etc

 
Gallery Image
Contractors
M/s. Prenit World LLP
Gallery Image
Consultants
M/s. KICONS Limited
 
Similar Projects

See Similar Projects

Similar Project

Procurement of Equipment for Burns unit (New Ward 118) Dept. of Plastic Surgery, GMC, Bambolim Goa – SH: SITC of Flash Autoclave

View Project
Similar Project

Replacement of lifts at Goa Medical College including comprehensive AMC at Bambolim, Goa

View Project
Similar Project

Supply, Installation, Testing and Commissioning of Cardiac Monitors, ECG machine, Defribrillators, etc.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.