Project Duration
Stipulated Date of Commencement
December 12 2011
Stipulated Date of Completion /
Likely Date of Completion April 11 2012
Likely Date of Completion April 11 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,528,636.00
Awarded for
₹ 5,976,204.30
Contractors
M/s. Ask Developers
Consultants
M/s. Datta Kare Associates
Sub Works
This project involved 1 sub works. The details of the same available below
1
Supply, Installation, Testing & Commissioning of Mortuary Cabinet.
100% completed
Project Duration
Stipulated Date of Commencement
December 01 2011
Stipulated Date of Completion /
Likely Date of Completion March 31 2012
Likely Date of Completion March 31 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,058,320.00
Awarded for
₹ 2,406,250.00
Contractors
M/s. Megastar Engineering
Consultants
M/s. Datta Kare Associates
See Similar Projects
Updating the work of provision of fire safety measures at Goa Medical College and Goa Dental College, Bambolim, Goa. -Civil works.
View Project
Construction of Girls Hostel at Goa Medical College and Hospital, Bambolim, Goa.
View Project
Renovation/ Maintenance of Hospitals, CHCs, PHCs, RMDs, under Directorate of Health Services in North, Goa – SH : Repair of two nos. of 60 KVA UPS installed at Sub District Hospital, Po+C523nda, Goa.
View Project