Project Duration
Stipulated Date of Commencement
July 23 2019
Stipulated Date of Completion /
Likely Date of Completion November 01 2019
Likely Date of Completion November 01 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,550,000.00
Awarded for
₹ 1,550,000.00
Project highlights
Project consists of supply, Installation, Testing and Commissioning of Anesthesia Workstation for extension of ward 125 for cardiology department
Contractors
M/s. Rescare Medysis I PVT. Ltd.
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD