Project Duration
Stipulated Date of Commencement
January 21 2013
Stipulated Date of Completion /
Likely Date of Completion May 20 2013
Likely Date of Completion May 20 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 411,664.00
Awarded for
₹ 492,000.00
Project highlights
Motruary Cabinet Works
Contractors
M/s. Megastar Engg., Pune
Consultants
M/s Effective Architectural Services
See Similar Projects
Supply, installation, testing and commissioning of 2 nos. of 30 KVA UPS
View Project
Upgradation of Ward Nos. 120, 123, 124, staff rest rooms and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa : SH – Procurement of additional works/items and medical equipments required for Ward No.125 and Cardiovascular Surgical Operation Theatre – Supply, Installation and Testing and Commissioning of Heart Lung Machine
View Project
Procurement of Equipment for the Burns Unit (New Ward 118), Department of Plastic Surgery, Goa Medical College, Bambolim – Goa -SH-Supply, Installation, Testing and Commissioning of Portable O.T. Light.
View Project