Project Duration
Stipulated Date of Commencement
September 12 2012
Stipulated Date of Completion /
Likely Date of Completion August 03 2013
Likely Date of Completion August 03 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 16,433,755.00
Awarded for
₹ 16,248,000.00
Project highlights
Furniture works
Contractors
M/s. Floor-Space
Consultants
M/s Effective Architectural Services
See Similar Projects
Upgradation of Community Health Center at Cacora, Curchorem
View Project
Renovation/Maintenance of Hospitals, CHCs, PHCs, and RMDs under Directorate of Health Services in North Goa –S.H : Maintenance/Renovation work of Community Health Centre at Bicholim – AMC for 200kVA Transformer at CHC Bicholim for 3 years (2019-2022).
View Project
Maintenance work of Goa Medical College & Hospital and Goa Dental College at Bambolim, Goa. S.H.: Maintenance Contract for 4 nos. of Emerson make 30 KVA UPS systems installed for Modular OTs 1-4 at Goa Medical College and Hospital, Bambolim for a period of three years.
View Project