Project Duration
Stipulated Date of Commencement
July 16 2010
Stipulated Date of Completion /
Likely Date of Completion January 15 2011
Likely Date of Completion January 15 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 14,521,313.00
Awarded for
₹ 13,783,266.21
Project highlights
Electrical & Fire Fighting work.
Contractors
M/s. Sunshine Electric Co. Pvt. Ltd.
Consultants
M/s Effective Architectural Services