Project Duration
Stipulated Date of Commencement
February 19 2010
Stipulated Date of Completion /
Likely Date of Completion August 18 2010
Likely Date of Completion August 18 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,316,000.00
Awarded for
₹ 3,432,000.00
Project highlights
Lift work.
Contractors
M/s. Thyssenkrupp Elevators (I) Pvt. Ltd.
Consultants
M/s Effective Architectural Services