Project Duration
Stipulated Date of Commencement May 31 2016
Stipulated Date of Completion /
Likely Date of Completion
June 30 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 745,000.00
Awarded for ₹ 818,000.00

Project highlights

Providing 2 bay & Scrub sink, PVC flooring and OT surgical lights

 
Gallery Image
Contractors
M/s.Mediotiz Installation
Gallery Image
Consultants
M/s. Datta Kare Associates
 
Similar Projects

See Similar Projects

Similar Project

Supply, Installation, Testing and Commissioning of Heart Lung machine

View Project
Similar Project

Minor Maintenance / Renovation works at Hospitals, Health Centres and Institutions under Directorate of Health Services, in the State of Goa – Exterior and Interior painting works

View Project
Similar Project

Construction of Primary Health Centre at Navelim, Margao, Goa. -HT Tapping work.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.