Project Duration
Stipulated Date of Commencement June 26 2009
Stipulated Date of Completion /
Likely Date of Completion
January 25 2010
Status
100%
Completed
Cost (₹)
Estimated at ₹ 50,52,760.00
Awarded for ₹ 5,122,999.00
 
Gallery Image
Contractors
M/s. Mohan Electricals
Gallery Image
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Supply, Installation, Testing and Commissioning of Token System

View Project
Similar Project

External electrical works at area around new Library Building and Power supply to new Library building at GMC Complex.

View Project
Similar Project

Minor Maintenance/ Renovation Works at Institute of Psychiatry and Human Behaviour, Bambolim, Goa SH: Carriage of Water.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.