Project Duration
Stipulated Date of Commencement
January 19 2014
Stipulated Date of Completion /
Likely Date of Completion March 18 2014
Likely Date of Completion March 18 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,292,648.00
Awarded for
₹ 1,373,377.55
Project highlights
Repairs / Upgradation & Maintenance of Old Primary Health Centre at Sanquelim, Goa
Contractors
M/s. Duracore Constructions
Consultants
M/s. Bhaskar Wagle and Associates