Project Duration
Stipulated Date of Commencement
June 16 2016
Stipulated Date of Completion /
Likely Date of Completion August 15 2016
Likely Date of Completion August 15 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,671,788.00
Awarded for
₹ 9,293,791.89
Project highlights
The work involves repairs of roofing, false ceiling, painting, etc.
Contractors
M/s. Sirajuddin Beig
Consultants
M/s. Bhaskar Wagle and Associates