Project Duration
Stipulated Date of Commencement
August 31 2013
Stipulated Date of Completion /
Likely Date of Completion September 30 2013
Likely Date of Completion September 30 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,044,105.30
Awarded for
₹ 1,095,570.00
Contractors
M/s. Paulbern Enterprises
Consultants
Datta Kare Associates