Project Duration
Stipulated Date of Commencement
April 02 2011
Stipulated Date of Completion /
Likely Date of Completion September 01 2011
Likely Date of Completion September 01 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 81,57,300.00
Awarded for
₹ 66,66,600.00
Contractors
M/s. MDD Medical Systems (I) Pvt. Ltd.
Consultants
Datta Kare Associates
See Similar Projects
S.H. Carriage of Water
View Project
Upgradation of Morgue situated at T. B. Sanatorium, Monte Hill, Margao -Civil, Plumbing & Electrical work.
View Project
External electrical work
View Project