Project Duration
Stipulated Date of Commencement July 23 2006
Stipulated Date of Completion /
Likely Date of Completion
October 22 2006
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,144,443.00
Awarded for ₹ 1,210,535.00
 
Gallery Image
Contractors
M/s. Chowgule Industries (I) Ltd.
Gallery Image
Consultants
M/s. Madhav Kamat & Associates
 
Similar Projects

See Similar Projects

Similar Project

Rear Side parking and Biomedical Waste Building

View Project
Similar Project

Supply, Testing and Commissioning of Ventilators with Humidifiers

View Project
Similar Project

Construction of IInd phase at Goa Dental College and Hospital at Bambolilm, Goa -Civil,Plumbing, internal electrical and fire fighting works-

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.