Project Duration
Stipulated Date of Commencement
September 19 2018
Stipulated Date of Completion /
Likely Date of Completion September 24 2018
Likely Date of Completion September 24 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 135,591.00
Awarded for
₹ 133,236.00
Project highlights
The scope of work includes HT tapping work for obtaining electricity connection to PHC Navelim.
Contractors
M/s. Voltas Engineering Pvt. Ltd.
Consultants
In-house (GSIDC)