Project Duration
Stipulated Date of Commencement
July 08 2019
Stipulated Date of Completion /
Likely Date of Completion August 22 2019
Likely Date of Completion August 22 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 35,100.00
Awarded for
₹ 32,760.00
Contractors
M/s. Powertrac Corporation
Consultants
In-house (GSIDC)