Project Duration
Stipulated Date of Commencement
October 30 2011
Stipulated Date of Completion /
Likely Date of Completion January 13 2012
Likely Date of Completion January 13 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,493,415.00
Awarded for
₹ 5,399,824.00
Contractors
M/s. Siemens Enterprises Communications Pvt. Ltd.
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.