Project Duration
Stipulated Date of Commencement
December 25 2010
Stipulated Date of Completion /
Likely Date of Completion May 24 2011
Likely Date of Completion May 24 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,13,89,800.00
Awarded for
₹ 2,08,76,500.00
Contractors
M/s. MGI (India) Pvt. Ltd.
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.
See Similar Projects
Supply, Installation, Testing and Commissioning of negative pressure VRDL lab at Goa Medical College and Hospital, Bambolim.