Project Duration
Stipulated Date of Commencement
May 01 2008
Stipulated Date of Completion /
Likely Date of Completion February 26 2009
Likely Date of Completion February 26 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 17,230,000.00
Awarded for
₹ 17,000,000.00
Contractors
M/s. Thyssenkrupp Elevators (I) Pvt. Ltd.
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.
See Similar Projects
HVAC Works.
View Project
Updating the work of provision of fire safety measures at Goa Medical College and Goa Dental College, Bambolim, Goa. -Civil works.
View Project
Repairs to Library Block at Goa Medical College & Hospital at Bambolim, Goa – Interior & electrical work.
View Project





