Project Duration
Stipulated Date of Commencement
March 03 2007
Stipulated Date of Completion /
Likely Date of Completion April 02 2009
Likely Date of Completion April 02 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 174,969,028.00
Awarded for
₹ 186,209,408.98
Project highlights
RCC five storeyed building.
Ground Floor : Casualty ward & morgue, O.T.
First Floor : Consulting rooms.
Second Floor : Surgical wards, OT (04 nos.), ICU.
Third Floor : Pediatric wards, gynecology wards, antenatal ward, post natal wards, OT, special & twin private rooms.
Fourth Floor : Medicine Ward (Male & Female), ICCU, Conference Room.
Contractors
M/s. IVRCL Infrastructure & Projects Ltd.
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.
See Similar Projects
Medical Gas & Other Connected works for OTs.
View Project
Civil, Plumbing, Electrical, Lift & Fire – Fighting works
View Project
Renovation/Maintenance of Hospitals, CHC’s, PHC’s, RMD’s under Directorate of Health Services in North Goa – S.H. Replacement of phase barrier sheets in HT panel of Megawin make and one time servicing of 33 KV HT outdoor breaker installed at Sub District Hospital, Ponda – Goa
View Project