Project Duration
Stipulated Date of Commencement
January 14 2022
Stipulated Date of Completion /
Likely Date of Completion April 13 2022
Likely Date of Completion April 13 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,695,125.00
Awarded for
₹ 2,072,768.94
Project highlights
Roofing works at Community Health Centre, Canacona
Contractors
M/s.Aditya P. Kamat Tarcar
Consultants
In-house (GSIDC)
See Similar Projects
Upgradation of Hospital facilities at Goa Medical College, Bambolim, Hospicio Hospital at Margao and RMD at Thane & Keri. SH- Upgradation of Ward Nos. 120, 123, 124, staff rest rooms and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa-Extension of Ward 125 for Cardiology Department at Goa Medical College, Bambolim-Goa.