Project Duration
Stipulated Date of Commencement
January 14 2022
Stipulated Date of Completion /
Likely Date of Completion April 13 2022
Likely Date of Completion April 13 2022
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,695,125.00
Awarded for
₹ 2,072,768.94
Project highlights
Roofing works at Community Health Centre, Canacona
Contractors
M/s.Aditya P. Kamat Tarcar
Consultants
In-house (GSIDC)
See Similar Projects
Renovations of old IPHB Building to accommodate Nursing Hostel and College and Directorate of Food & Drugs
View Project
Upgradation of Hospital facilities at Goa Medical College, Bambolim, Hospicio Hospital at Margao and RMD at Thane & Keri. SH- Upgradation of Ward Nos. 120, 123, 124, staff rest rooms and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa -Extension of Ward 125 for Cardiology Department at Goa Medical College, Bambolim-Goa – Supply, Installation in specified location, Testing and Commissioning of Advanced Non Invasive Ventilator with Humidifier including Compressor
View Project
Construction of compound wall for the Goa Medical College, Hospital at Bambolim, Goa.
View Project