Project Duration
Stipulated Date of Commencement
March 08 2019
Stipulated Date of Completion /
Likely Date of Completion June 07 2019
Likely Date of Completion June 07 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 18,195,717.00
Awarded for
₹ 20,317,614.73
Project highlights
Furniture and Interior Works
Contractors
M/s. Decor Home (India) Pvt. Ltd.
Consultants
M/s Vijaykumar Sawant Associates.,
See Similar Projects
External electrical work at area around new Library Building and Power supply to new Library Building, GMC Complex, Bambolim, Goa – Supply, laying of 1100 V power supply cable.
View Project
Procurement of Equipment for the Burns Unit (New Ward 118), Department of Plastic Surgery, Goa Medical College, Bambolim –Goa -SH-Supply, Installation, Testing and Commissioning of Central Nursing Station monitor and Multichannel monitors (5 channels with IBP Monitoring)
View Project
Supply, Testing and Commissioning of Battery Operated Sternal Saw and Electrically operated Sternal Saw
View Project