Project Duration
Stipulated Date of Commencement March 26 2007
Stipulated Date of Completion /
Likely Date of Completion
June 25 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 9,488,696.00
Awarded for ₹ 8,161,350.00
 
Gallery Image
Contractors
M/s. MGI (I) Pvt. Ltd.
Gallery Image
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Renovation/Maintenance of Hospitals, CHCs, PHCs, and RMDs under Directorate of Health Services in North Goa –S.H : Maintenance/Renovation work of Community Health Centre at Bicholim – AMC for 200kVA Transformer at CHC Bicholim for 3 years (2019-2022).

View Project
Similar Project

STP & ETP works

View Project
Similar Project

Supply, installation, testing, commissioning of fire detection and alarm system

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.