Project Duration
Stipulated Date of Commencement
March 26 2007
Stipulated Date of Completion /
Likely Date of Completion June 25 2007
Likely Date of Completion June 25 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 17,671,482.00
Awarded for
₹ 18,007,783.00
Contractors
M/s. MGI (I) Pvt. Ltd.
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
See Similar Projects
Sewage treatment plant at 30 KLD capacity
View Project
Interior works
View Project
Civil, Plumbing, Electrical, Lift & Fire – Fighting works
View Project





