Project Duration
Stipulated Date of Commencement
September 01 2007
Stipulated Date of Completion /
Likely Date of Completion November 15 2007
Likely Date of Completion November 15 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 15,221,765.00
Awarded for
₹ 16,545,265.00
Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.