Project Duration
Stipulated Date of Commencement
June 30 2007
Stipulated Date of Completion /
Likely Date of Completion September 29 2007
Likely Date of Completion September 29 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 19,289,000.00
Awarded for
₹ 20,999,732.00
Project highlights
Furniture, false ceiling, partitions, signages, storage cabinets, workstations, modular furniture, etc.
Contractors
M/s. Damian de Goa
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
See Similar Projects
Major Maintenance Work of Goa Medical College and Hospital at Bambolim, Goa Major Maintenance Work of Goa Medical College and Hospital at Bambolim, Goa. SH : Maintenance of Split, Window Type, Mega split, Multi split and Tower type Air Conditioners installed in GMC Complex, Bambolim (2020-2023)
View Project
Additional infrastructure works for GMC & H – Demolition & construction of Hospital and Hostel at Mandur, Goa – S.H. – Furniture and interior works
View Project
Supply, Installation, Testing and Commissioning of Cardiac Monitors, ECG machine, Defribrillators, etc.
View Project