Project Duration
Stipulated Date of Commencement
June 30 2007
Stipulated Date of Completion /
Likely Date of Completion September 29 2007
Likely Date of Completion September 29 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 19,289,000.00
Awarded for
₹ 20,999,732.00
Project highlights
Furniture, false ceiling, partitions, signages, storage cabinets, workstations, modular furniture, etc.
Contractors
M/s. Damian de Goa
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.