Project Duration
Stipulated Date of Commencement
November 30 2020
Stipulated Date of Completion /
Likely Date of Completion March 10 2021
Likely Date of Completion March 10 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,678,633.00
Awarded for
₹ 36,51,527.60 part amount of 83,24,187.60
Project highlights
Exterior and Interior painting works at Community Health Centre, Bicholim, Community Health Centre, Tuem
Contractors
M/s.H. Candolcar & Sons
Consultants
In-house (GSIDC)
See Similar Projects
Maintenance works at Goa Medical College and Hospital S.H.: Maintenance Contract for 4 nos. of Emerson make 30 KVA UPS systems installed for Modular OTs 1-4 at Goa Medical College and Hospital, Bambolim for six months
View Project
Maintenance work of Goa Medical College & Hospital and Goa Dental College at Bambolim, Goa. S.H.: Supply, Installation, Testing & Commissioning of 30KVA online UPS systems for ICU 123 and Modular OT 5 at Goa Medical College.
View Project
Construction of District Hospital at Mapusa, Goa
View Project