Project Duration
Stipulated Date of Commencement
November 30 2020
Stipulated Date of Completion /
Likely Date of Completion March 10 2021
Likely Date of Completion March 10 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,678,633.00
Awarded for
₹ 36,51,527.60 part amount of 83,24,187.60
Project highlights
Exterior and Interior painting works at Community Health Centre, Bicholim, Community Health Centre, Tuem
Contractors
M/s.H. Candolcar & Sons
Consultants
In-house (GSIDC)