Project Duration
Stipulated Date of Commencement December 21 2018
Stipulated Date of Completion /
Likely Date of Completion
May 20 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 10,062,232.00
Awarded for ₹ 9,584,411.00

Project highlights

Construction of internal concrete road joining school building and hostels and laying of pavers for footpath.

 
Gallery Image
Contractors
M/s. Impact Infraheights Pvt. Ltd.,
Gallery Image
Consultants
M/s. Ulysis
 
Similar Projects

See Similar Projects

Similar Project

Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa – Civil, Plumbing and Electrical works-Bicholim Taluka (G.H.S and G.P.S. Kasarpal)

View Project
Similar Project

Supply & Fixing of Ceramic Green Chalk Boards for Government Schools/ Colleges in the state of Goa

View Project
Similar Project

Repairs/Upgradation & Maintenance of Government Schools in the State of Goa – Civil, Plumbing & Electrical works in Dharbandora Taluka – Package VIII (Rate Contract)

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.