Project Duration
Stipulated Date of Commencement
September 22 2011
Stipulated Date of Completion /
Likely Date of Completion June 21 2012
Likely Date of Completion June 21 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,062,925.00
Awarded for
₹ 6669089.99
Project highlights
Construction of Anganwadi Centres
Contractors
M/s. Ask Developers
Consultants
M/s. Datta Kare Associates
See Similar Projects
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa – Civil, Plumbing and Electrical works in Bicholim Taluka- Package A-(G.P.S. Kahtar Dabdaba, G.P.S. Lamgao, G.P.S. Bagwada Pilgao, G.P.S. Mathwada Pilgao)
View Project
Construction of Compound Wall for Ashram school under centrally sponsored scheme of Ministry of Tribal Affairs at “MOSHIPHOND” in the Land under Survey no. 20/0 in the Village Poinguinim of Canacona Taluka.
View Project
Repairs/Upgradation & maintenance of Government Schools in State of Goa – Civil, Plumbing & Electrical works – Package G (Quepem Taluka) – GPS Corla, GPMS Kanibag
View Project