Project Duration
Stipulated Date of Commencement
August 31 2012
Stipulated Date of Completion /
Likely Date of Completion December 30 2013
Likely Date of Completion December 30 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 132,283,918.00
Awarded for
₹ 156,121,530.72
Project highlights
Upgraded infrastructure for Govt. College of Arts, Science & Commerce at Khandola marcel, Goa
Contractors
M/s.M V Roa Infra Projects Pvt Ltd
Consultants
M/s. KICONS Limited