Project Duration
Stipulated Date of Commencement
November 30 2019
Stipulated Date of Completion /
Likely Date of Completion July 29 2020
Likely Date of Completion July 29 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 14,689,939.00
Awarded for
₹ 11,974,787.00
Project highlights
furniture work
Contractors
M/s. Infiniti Modules Pvt. Ltd.,
Consultants
M/s.Banaji & Associates