Project Duration
Stipulated Date of Commencement
June 14 2013
Stipulated Date of Completion /
Likely Date of Completion July 28 2013
Likely Date of Completion July 28 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,056,644.00
Awarded for
₹ 10,977,261.50
Project highlights
Lab furniture work
Contractors
M/s. Amardeep Designers India Pvt. Ltd.
Consultants
M/s. Banaji & Associates