Status

Completed
 
Gallery Image
Contractors
Gallery Image
Consultants
 

Sub Works

This project involved 2 sub works. The details of the same available below

1

Civil, Plumbing & Electrical works.

100% completed
 
Project Duration
Stipulated Date of Commencement December 27 2013
Stipulated Date of Completion /
Likely Date of Completion
January 08 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 73,214,248.00
Awarded for ₹ 85,526,271.00
 
Contractors
Contractors
M/s. R. B. S. Candiaparcar
Consultants
Consultants
M/s. Datta Kare Associates
2

Furniture work.

100% completed
 
Project Duration
Stipulated Date of Commencement February 27 2015
Stipulated Date of Completion /
Likely Date of Completion
April 26 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 7,323,598.00
Awarded for ₹ 6,353,797.50
 
Contractors
Contractors
M/s. Amardeep Designers India Pvt. Ltd.
Consultants
Consultants
M/s. Datta Kare Associates
Similar Projects

See Similar Projects

Similar Project

Construction of new school building for Govt. Primary School Murmuse Tuem in Pernem

View Project
Similar Project

Repairs/Upgradation and maintenance of Government schools in the state of Goa – Package B (GPS Hivre Budruk, GPS Pal, GPS Kudshe, GMS Kudshe)

View Project
Similar Project

Repairs/Upgradation & Maintenance Of Government Schools In The State Of Goa – Civil, Plumbing & Electrical Works – Package-I (Pernem Taluka) – Rate Contract

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.