Project Duration
Stipulated Date of Commencement
April 04 2018
Stipulated Date of Completion /
Likely Date of Completion March 07 2018
Likely Date of Completion March 07 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,004,938.00
Awarded for
₹ 944,596.00
Project highlights
Repair/Upgrdation works of schools which includes roofing ,tiling,dadoes,painting etc.