Project Duration
Stipulated Date of Commencement
August 03 2015
Stipulated Date of Completion /
Likely Date of Completion January 02 2016
Likely Date of Completion January 02 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 14,138,334.44
Awarded for
₹ 16,700,040.00
Project highlights
painting of schools, flooring, roofing, structural repairs etc.
Contractors
M/s. Shivam Infratech
Consultants
M/s. Creative Abode
See Similar Projects
Repairs/Upgradation & Maintenance of Government Schools in the State of Goa – Civil, Plumbing & Electrical works in Bicholim Taluka – Package F (G.P.S. Kelbaiwada Mayem, G.P.S. Borde, G.P.S. Bhavkai Mayem, G.P.S. Haldonwadi Mayem ).
View Project
Furnishing Work of Ashram school under centrally sponsored scheme of Ministry of Tribal Affairs at “MOSHIPHOND” in the Land under Survey no. 20/0 in the Village Poinguinim of Canacona Taluka.
View Project
Repairs, Upgradation & Maintenance of Government Schools in the State of Goa – Packge O (Sattari Taluka) – (GPS, Gaonkarwada Vantem, GPS Vantem, GPS Advoi)
View Project