Project Duration
Stipulated Date of Commencement
March 04 2014
Stipulated Date of Completion /
Likely Date of Completion June 03 2014
Likely Date of Completion June 03 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,000,000.00
Awarded for
₹ 5,000,000.00
Project highlights
Repairs and renovation of roofing, to 06 number of Government Primary schools in Canacona Taluka in this package.
Contractors
M/s.K G Thomas
Consultants
M/s.Manoj Amshekar
See Similar Projects
Repairs/upgradation & maintenance of Government primary Schools in the state of Goa -Civil, plumbing and electrical works-package A – GPS Ghadiwada GPS Deulmol Sirvoi, GPS Deulamol Markarnem and GPS Pontemol.
View Project
Infrastructure Works For Sanjay Centre For Special Education at Bogda, Vasco -SH:Fire safety and exit signages work
View Project
Repairs/Upgradation & Maintenance of Govt. Schools in the State of Goa- (Ponda Taluka) – (GPS Konse, GPS Makadsai, GPS Gothawada,GPS Kodar,GPS Bonbag & GPS Shignewhal )
View Project