Project Duration
Stipulated Date of Commencement
December 11 2018
Stipulated Date of Completion /
Likely Date of Completion December 25 2019
Likely Date of Completion December 25 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,228,751.00
Awarded for
₹ 13,014,410.12
Project highlights
Repairs/Renovation works
Contractors
M/s. A. Y. Gulumkar
Consultants
M/s. Manoj M. Amshekar