Project Duration
Stipulated Date of Commencement
September 28 2017
Stipulated Date of Completion /
Likely Date of Completion September 27 2018
Likely Date of Completion September 27 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,000,000.00
Awarded for
₹ 10,843,530.62
Project highlights
Repairs/ Upgradation & Maintenance of schools
Contractors
M/s.Sirajuddin Beig
Consultants
M/s.S.H. Patil (PMC)
See Similar Projects
Repairs/Upgradation & Maintenance of Government Schools in the State of Goa – Package N – Sattari Taluka – GPS Nanus, GPS Zarme,GPS Dabem, GPS Kumthol, GPS Karanzol, GPS Karmali Budruk) – Balance works.
View Project
Extension / upgradation of Government college of Arts, Science & Commerce at Khandola, Marcel, Goa -HVAC work
View Project
Repairs/Upgradation and Maintenance of Government Primary Schools in the State of Goa Sanguem Taluka – (GPS Periudak, GPS Devnamol, GPS Mugoli, GPS Taripanta, GPS Curpem)
View Project