Project Duration
Stipulated Date of Commencement
September 28 2017
Stipulated Date of Completion /
Likely Date of Completion September 27 2018
Likely Date of Completion September 27 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,000,000.00
Awarded for
₹ 10,843,530.62