Project Duration
Stipulated Date of Commencement
June 29 2018
Stipulated Date of Completion /
Likely Date of Completion January 08 2019
Likely Date of Completion January 08 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,490,150.00
Awarded for
₹ 8,107,253.90
Project highlights
Repairs/ Upgradation & Maintenance of schools
Contractors
M/s.Nilambari Constructions
Consultants
M/s.Allwyn Crasto
See Similar Projects
Interior, Electrical and Lift work
View Project
Repairs/ Upgradation & Maintenance of Government Schools in the State of Goa – Civil, Plumbing & Electrical – GHS Zambaulim
View Project
Repairs/Upgradation & Maintenance of Government Schools In the State of Goa – Pernem Taluka: Package – V (GPS Tiwade Dhargal, GPS Chandel, GPS Madkai Ozari, GPS Varkhand, GPS Bhatpavni, GPS Patradevi, GPS Fakirpata Torse, GPS Tulaskarwadi)