Project Duration
Stipulated Date of Commencement
May 19 2015
Stipulated Date of Completion /
Likely Date of Completion October 18 2015
Likely Date of Completion October 18 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 13,241,301.43
Awarded for
₹ 16,657,086.72
Project highlights
painting of schools, flooring, roofing, structural repairs etc.
Contractors
M/s. K. G. Thomas
Consultants
M/s. Creative Abode
See Similar Projects
Repair/ Upgradation & Maintenance of Government Schools in the State of Goa- Package B-Canacona Taluka. (GPS Amona, GPS Bhuper, GPS Marlim, GPS Shishegal, GPS Tudal)