Project Duration
Stipulated Date of Commencement
December 02 2019
Stipulated Date of Completion /
Likely Date of Completion June 10 2020
Likely Date of Completion June 10 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,570,096.00
Awarded for
₹ 4,498,179.10
Project highlights
Repairs/Upgradation & maintenance of Government Schools
Contractors
M/s. Sushant Khedekar
Consultants
M/s. Manoj M. Amshekar