Project Duration
Stipulated Date of Commencement
September 12 2018
Stipulated Date of Completion /
Likely Date of Completion July 26 2019
Likely Date of Completion July 26 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,756,594.00
Awarded for
₹ 13,018,832.84
Project highlights
Repairs/Upgradation & maintenance of Government Schools
Contractors
M/s. Shree Hari Krishna Constructions
Consultants
M/s. Manoj M. Amshekar
See Similar Projects
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa – Civil, Plumbing and Electrical works-Bicholim Taluka – Package H (G.P.S Kharekhajan- Virdi, G.P.S Kudchire, G.P.S. Pratap Nagar- Harvalem, G.H.S. Late Jayendra J. Rane- Kudchire)
View Project
Repairs /Upgradation & Maintenance of Government schools in the state of Goa -Civil,Plumbing & Electrical works – Package IV-D
View Project
Construction of Government College of Commerce & Economics at Borda, Margao, Goa – Civil, plumbing, electrical, lift and fire fighting – Phase I.
View Project