Project Duration
Stipulated Date of Commencement
February 26 2014
Stipulated Date of Completion /
Likely Date of Completion July 25 2014
Likely Date of Completion July 25 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,09,75,951.00
Awarded for
₹ 2,44,73,933.00
Project highlights
Repairs and upgradation of Govt High school Malkarne and Govt. High school Balli
Contractors
M/s.K G Thomas
Consultants
Shri Manoj M. Amshekar
See Similar Projects
Repairs/Upgradation & Maintenance of Government schools in the State of Goa – Quepem Taluka – Package F.
View Project
Construction of Football ground at Zariwada, Davorlim, Dicapale, Salcete Goa
View Project
Construction of Ashram school under Centrally sponsored scheme of Ministry of Tribal affaires at Moshiphond in the Village Ponguinim of Canacona Taluka.
View Project





