Project Duration
Stipulated Date of Commencement
February 26 2014
Stipulated Date of Completion /
Likely Date of Completion July 25 2014
Likely Date of Completion July 25 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,09,75,951.00
Awarded for
₹ 2,44,73,933.00
Project highlights
Repairs and upgradation of Govt High school Malkarne and Govt. High school Balli
Contractors
M/s.K G Thomas
Consultants
Shri Manoj M. Amshekar
See Similar Projects
Repairs/Upgradation and maintenance of Government schools in the state of Goa –Package B (Salcete Taluka) – (GPS Baradi, GPS Chandor, GMS Sao Jose de Areal, GPS Gudi Paroda) – 4th call