Project Duration
Stipulated Date of Commencement
February 15 2019
Stipulated Date of Completion /
Likely Date of Completion October 15 2019
Likely Date of Completion October 15 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,409,948.00
Awarded for
₹ 12,785,000.00
Project highlights
Repairs/Upgradation & Maintenance of Govt. schools in the state of Goa
Contractors
M/s. M. M. Naik & Co.
Consultants
M/s. Bhaskar Wagle & Associates
See Similar Projects
Construction of Anganwadi Centres from NABARD Assistance – Package II (GPS Sangao Ozari, GPS Sakral Torse).
View Project
Repairs/Upgradation & maintenance of Government Schools in State of Goa – Civil, Plumbing & Electrical works – Package D – Quepem Taluka (GPS Katta Fatorpa, GPS Shirlim)
View Project
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa – Civil, Plumbing and Electrical works-Bicholim Taluka (G.H.S and G.P.S. Kasarpal)
View Project





