Project Duration
Stipulated Date of Commencement
Stipulated Date of Completion /
Likely Date of Completion July 15 2020
Likely Date of Completion July 15 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 15,701,123.00
Awarded for
₹ 18,139,310.37
Project highlights
Repairs/Upgradation & Maintenance of Govt. schools in the state of Goa
Contractors
M/s. Sun Infrastructures
Consultants
M/s. Vaishali Pednekar Associates